Model Table PROJECT ACTIVITY PERFORMANCE ANALYSIS

Attributes

Attribute Description (where applicable)
Activity Seq KeyRepresents the Activity Sequence Key of the fact
Fact Project Activity Performance Analysis IDProject Activity Performance Analysis ID

Measures (table to be generated as far as possible)

Aggregation of measures is based on SUM if not explicitly noted.

This section describes the basic measures in the cube. These are either measures defined in the core Information Source, in the model itself or in the ETL process. The columns have the following meaning:

Measure Calculated Y/N Contains Time Intelligence Y/N Definition/Note (where applicable) Aggregation Type Hidden Y/N Tabular Expression
ACWPNNNSUM([ACWP_COL])
ACWP RCYYReporting Currency calculationNSUM([REP_CURR_ACWP])/[Currency Rate]
BACNNNSUM([BAC_COL])
BAC RCYYReporting Currency calculationNSUM([REP_CURR_BAC])/[Currency Rate]
BCWPNNNSUM([BCWP_COL])
BCWP RCYYReporting Currency calculationNSUM([REP_CURR_BCWP])/[Currency Rate]
BCWSNNNSUM([BCWS_COL])
BCWS RCYYReporting Currency calculationNSUM([REP_CURR_BCWS])/[Currency Rate]
Count ActivityNNNSUM([COUNT_ACTIVITY])
Count Cancelled ActivityNNNSUM([COUNT_CANCELLED_ACTIVITY])
Count Closed ActivityNNNSUM([COUNT_CLOSED_ACTIVITY])
Count Completed ActivityNNNSUM([COUNT_COMPLETED_ACTIVITY])
Count Late Planned ActivityNNNSUM([COUNT_LATE_PLANNED_ACTIVITY])
Count Late Released ActivityNNNSUM([COUNT_LATE_RELEASED_ACTIVITY])
Count Planned ActivityNNNSUM([COUNT_PLANNED_ACTIVITY])
Count ProjectsNNProject Currency calculationNDISTINCTCOUNT('PROJECT ACTIVITY PERFORMANCE ANALYSIS'[DIM_PROJECT_ID])
Count Released ActivityNNNSUM([COUNT_RELEASED_ACTIVITY])
CVNNNSUM([CV_COL])
CV RCYYReporting Currency calculationNSUM([REP_CURR_CV])/[Currency Rate]
EACNNNSUM([EAC_COL])
EAC RCYYReporting Currency calculationNSUM([REP_CURR_EAC])/[Currency Rate]
ETCNNNSUM([ETC_COL])
ETC RCYYReporting Currency calculationNSUM([REP_CURR_ETC])/[Currency Rate]
IEACNNNSUM([IEAC_COL])
IEAC RCYYReporting Currency calculationNSUM([REP_CURR_IEAC])/[Currency Rate]
IETCNNNSUM([IETC_COL])
IETC RCYYReporting Currency calculationNSUM([REP_CURR_IETC])/[Currency Rate]
IVACNNNSUM([IVAC_COL])
IVAC RCYYReporting Currency calculationNSUM([REP_CURR_IVAC])/[Currency Rate]
SVNNNSUM([SV_COL])
SV RCYYReporting Currency calculationNSUM([REP_CURR_SV])/[Currency Rate]
VACNNNSUM([VAC_COL])
VAC RCYYReporting Currency calculationNSUM([REP_CURR_VAC])/[Currency Rate]
CPIYNNIF( [ACWP]>0, round([BCWP]/[ACWP],2),IF( [BCWP]>0, 1 ,BLANK()))
Completed Activities %YNNIF([Count Activity]>0, [Count Completed Activity]/[Count Activity], 0)
Actual vs Scheduled %YNNIF([BCWS] > 0, [ACWP]/[BCWS], BLANK())
Actual vs Scheduled % RCNYReporting Currency calculationNIF([BCWS RC] > 0, [ACWP RC]/[BCWS RC], BLANK())
CPI RCNYReporting Currency calculationNIF( [ACWP RC]>0, round([BCWP RC]/[ACWP RC],2),IF( [BCWP RC]>0, 1 ,BLANK()))
SPIYNNIF( [BCWS]>0, round([BCWP]/[BCWS],2),IF( [BCWP]>0, 1, BLANK()))
SPI RCNYReporting Currency calculationNIF( [BCWS RC]>0, round([BCWP RC]/[BCWS RC],2),IF( [BCWP RC]>0, 1, BLANK()))

Time Intelligence Measures

Time based measures are calculated in the cube with respect to other measures. The table below defines the meaning/definition of  the different time measures. These measures need to be used with a specific time dimension hierarchy [REPORTING_DATE].[RepDateMFHy].

Measure Meaning
Ytd Aggregated value for current month in current  year. E.g. for period 201210 Ytd represents sum of periods 201200-201210.
R12 For a given period, the sum all months from one year back up to the previous month. E.g. Rolling 12 for 201210 is the sum of months 201110 - 201209
PY Previous Year
The value of the corresponding month one year back. E.g. for month 201210, the value of month 201110.
YTD PY Year to Date Previous Year
Aggregated value for corresponding month one year back. E.g. for month 201210 YTD Previous Year represents sum of months 201101-201110.
R12 PY Rolling 12 (completed) Months Previous Year
For a given month, first going one year back, then taking the sum of all months from one (more) year back up to the previous month. E.g. for month 201210 the sum of month 201010-201109
Avg XXX Ytd Sum XXX YTD/Count XXX YTD
Avg XXX R12 Sum XXX R12/Count XXX R12
XXX % YTD Count XXX YTD/Count YYY YTD
XXX % R12 Count XXX R12/Count XXX R12

USED BY MODEL(S)

Model Name Product Area

Data source Information

The data source for this object is defined using IFS Developer Tool. The data source contains a number of transformations where the model reads data from the last step, i.e. the Data source view name (DW Source View Name).

Link to information source documentation: . http://blablabla to be generated...

Model Table DW Source view (SQL Server) BI Access View Referenced Information Source Recommended Access Type
PROJECT ACTIVITY PERFORMANCE ANALYSISFACT_ACTIVITY_CALCULATION_TMFACT_ACTIVITY_CALCULATION_BIFACT_ACTIVITY_CALCULATIONOn Line

SPECIAL INFO