Attribute | Description (where applicable) |
Activity Seq Key | Represents the Activity Sequence Key of the fact |
Fact Project Activity Performance Analysis ID | Project Activity Performance Analysis ID |
Aggregation of measures is based on SUM if not explicitly noted.
This section describes the basic measures in the cube. These are either measures defined in the core Information Source, in the model itself or in the ETL process. The columns have the following meaning:
Measure | Calculated Y/N | Contains Time Intelligence Y/N | Definition/Note (where applicable) | Aggregation Type | Hidden Y/N | Tabular Expression |
ACWP | N | N | N | SUM([ACWP_COL]) | ||
ACWP RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_ACWP])/[Currency Rate] | |
BAC | N | N | N | SUM([BAC_COL]) | ||
BAC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_BAC])/[Currency Rate] | |
BCWP | N | N | N | SUM([BCWP_COL]) | ||
BCWP RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_BCWP])/[Currency Rate] | |
BCWS | N | N | N | SUM([BCWS_COL]) | ||
BCWS RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_BCWS])/[Currency Rate] | |
Count Activity | N | N | N | SUM([COUNT_ACTIVITY]) | ||
Count Cancelled Activity | N | N | N | SUM([COUNT_CANCELLED_ACTIVITY]) | ||
Count Closed Activity | N | N | N | SUM([COUNT_CLOSED_ACTIVITY]) | ||
Count Completed Activity | N | N | N | SUM([COUNT_COMPLETED_ACTIVITY]) | ||
Count Late Planned Activity | N | N | N | SUM([COUNT_LATE_PLANNED_ACTIVITY]) | ||
Count Late Released Activity | N | N | N | SUM([COUNT_LATE_RELEASED_ACTIVITY]) | ||
Count Planned Activity | N | N | N | SUM([COUNT_PLANNED_ACTIVITY]) | ||
Count Projects | N | N | Project Currency calculation | N | DISTINCTCOUNT('PROJECT ACTIVITY PERFORMANCE ANALYSIS'[DIM_PROJECT_ID]) | |
Count Released Activity | N | N | N | SUM([COUNT_RELEASED_ACTIVITY]) | ||
CV | N | N | N | SUM([CV_COL]) | ||
CV RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_CV])/[Currency Rate] | |
EAC | N | N | N | SUM([EAC_COL]) | ||
EAC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_EAC])/[Currency Rate] | |
ETC | N | N | N | SUM([ETC_COL]) | ||
ETC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_ETC])/[Currency Rate] | |
IEAC | N | N | N | SUM([IEAC_COL]) | ||
IEAC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_IEAC])/[Currency Rate] | |
IETC | N | N | N | SUM([IETC_COL]) | ||
IETC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_IETC])/[Currency Rate] | |
IVAC | N | N | N | SUM([IVAC_COL]) | ||
IVAC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_IVAC])/[Currency Rate] | |
SV | N | N | N | SUM([SV_COL]) | ||
SV RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_SV])/[Currency Rate] | |
VAC | N | N | N | SUM([VAC_COL]) | ||
VAC RC | Y | Y | Reporting Currency calculation | N | SUM([REP_CURR_VAC])/[Currency Rate] | |
CPI | Y | N | N | IF( [ACWP]>0, round([BCWP]/[ACWP],2),IF( [BCWP]>0, 1 ,BLANK())) | ||
Completed Activities % | Y | N | N | IF([Count Activity]>0, [Count Completed Activity]/[Count Activity], 0) | ||
Actual vs Scheduled % | Y | N | N | IF([BCWS] > 0, [ACWP]/[BCWS], BLANK()) | ||
Actual vs Scheduled % RC | N | Y | Reporting Currency calculation | N | IF([BCWS RC] > 0, [ACWP RC]/[BCWS RC], BLANK()) | |
CPI RC | N | Y | Reporting Currency calculation | N | IF( [ACWP RC]>0, round([BCWP RC]/[ACWP RC],2),IF( [BCWP RC]>0, 1 ,BLANK())) | |
SPI | Y | N | N | IF( [BCWS]>0, round([BCWP]/[BCWS],2),IF( [BCWP]>0, 1, BLANK())) | ||
SPI RC | N | Y | Reporting Currency calculation | N | IF( [BCWS RC]>0, round([BCWP RC]/[BCWS RC],2),IF( [BCWP RC]>0, 1, BLANK())) |
Time based measures are calculated in the cube with respect to other measures. The table below defines the meaning/definition of the different time measures. These measures need to be used with a specific time dimension hierarchy [REPORTING_DATE].[RepDateMFHy].
Measure | Meaning |
Ytd |
Aggregated value for current month in current year. E.g.
for period 201210 Ytd represents sum of periods 201200-201210. |
R12 |
For a given period, the sum all months from one year back up to the
previous month. E.g. Rolling 12 for 201210 is the sum of months 201110
- 201209 |
PY |
Previous Year The value of the corresponding month one year back. E.g. for month 201210, the value of month 201110. |
YTD PY |
Year to Date Previous Year Aggregated value for corresponding month one year back. E.g. for month 201210 YTD Previous Year represents sum of months 201101-201110. |
R12 PY |
Rolling 12 (completed) Months Previous Year For a given month, first going one year back, then taking the sum of all months from one (more) year back up to the previous month. E.g. for month 201210 the sum of month 201010-201109 |
Avg XXX Ytd | Sum XXX YTD/Count XXX YTD |
Avg XXX R12 | Sum XXX R12/Count XXX R12 |
XXX % YTD | Count XXX YTD/Count YYY YTD |
XXX % R12 | Count XXX R12/Count XXX R12 |
Model Name | Product Area |
The data source for this object is defined using IFS Developer Tool. The data source contains a number of transformations where the model reads data from the last step, i.e. the Data source view name (DW Source View Name).
Link to information source documentation: . http://blablabla to be generated...
Model Table | DW Source view (SQL Server) | BI Access View | Referenced Information Source | Recommended Access Type |
PROJECT ACTIVITY PERFORMANCE ANALYSIS | FACT_ACTIVITY_CALCULATION_TM | FACT_ACTIVITY_CALCULATION_BI | FACT_ACTIVITY_CALCULATION | On Line |